When a developer says the app is 90% done, he is usually reporting how much has been written, not how much is left. The last 10% often takes as long as the first 90. This is a saying used in the industry, and we are going to break down how to navigate this situation when it arises.
Why the number is hard to trust
Programmers have joked about this since the 1980s. Tom Cargill of Bell Labs is credited with the rule: the first 90 percent of the code takes the first 90 percent of the development time, and the remaining 10 percent takes the other 90 percent.[1] The figures add up to 180 percent, which is the point. Jon Bentley made the line widely known in a 1985 column in Communications of the ACM.[1] The cause, in short, is that teams fail to foresee the hard and unpredictable parts when they estimate.[1]
Most developers who say "90%" are not lying. They are guessing, and a percentage needs something to be a percentage of. If the work is a complete list of tasks, 90% means nine in ten are finished. On a stuck project that list often doesn't exist. Without it, "90%" is a feeling, about as reliable as picking a slot machine in Las Vegas by intuition and hoping the next pull wins.
What the last 10% tends to hold
The part of an app you can see is screens, forms and buttons. That part often looks finished in a demo. The work a demo hides comes later: what happens when a payment fails, when two people edit the same record, or when the data is wrong. Then there is setting up the live hosting, testing with real data and fixing what the testing finds.
None of this shows on a screen, so none of it counts toward the percentage. That is why an app can look 90% done and still be months from launch.
Five questions to ask this week
1. Ninety percent of what? Ask for a written list of the remaining work. Each item should be in plain words, with an estimate in hours. If the developer can list it, you can add it up and compare it with what you pay. If he can't, the 90% has nothing behind it.
2. What was the number a month ago? Write down the date and the figure each time you hear one. A project that went from 70% to 80% to 90% and has sat at 90% for two months is not moving. The estimate moves, and the work doesn't. Real progress shows up as a shorter list.
The list can also grow for a good reason. As a product takes shape, features and tasks come to light that no one could see at the start. When that new work is something you want, a later deadline is an acceptable price, and a developer who tells you so is doing his job. Ask him to show what was added and why. Teams on projects of every budget face this choice.
3. Can I use it myself? Ask for a link to a test version you can click through, not a screen recording. A short paid job also tells you more than any status report; I cover how to set one up in how to hire custom software developers when you can't read code.
4. Can someone else run it? Ask a developer who has never seen the project to set it up from the code repository on a clean computer. The repository and the hosting account should be in your company's name. The checks are in what to find out before you hire custom software developers again. If setup takes days, or only the original developer can do it, the project depends on one person, and "almost done" means less than it sounds.
5. What could stop this from shipping? A developer who has thought about the end names real risks: a payment provider he hasn't connected, data he hasn't moved, a part he hasn't tested. "Nothing" is a worse answer than a long list.
This question tests your trust in the developer. A late release can cost real money, and it can still have a good reason, so hear the answer out. If you sell to other businesses, you may have to go to your own customers and ask for more time. You are not only the founder or owner. You are also the sales executive and the account manager, and that conversation is part of the job.
When the number stays at 90
You pay for each month the number doesn't move. If the answers to the five questions come back vague, or the list of remaining work keeps growing, the project needs a second opinion before the next invoice.
I saw this on a project I call Company C, a content management system that was about 6 months past its deadline and over budget. Five developers kept missing feature targets and ignoring the design specifications. Within a month I found which engineers could not follow direction or learn the frameworks, and the owner let three go. I trained the remaining developer, and the project finished in 3 months. I wrote up the whole case in what a software rescue consultant does.
An independent review of the code and the list of remaining work shows whether the end is near. It also gives you a cost and a time for reaching it. A quick number from someone who hasn't read the code is a guess. Sometimes a developer admits this and says he needs a few days to review the work before he can give you a firm figure. That answer can sound like stalling, and some founders drop the developer for it. If that sounds familiar, it may be worth a second look at that decision. Part of serving a client well is telling him what he doesn't want to hear, and "I don't know yet" is often the true answer. The one to question is the developer who says "90%" and can't show you the list.
Sources
- Wikipedia, "Ninety–ninety rule" (cites Jon Bentley, "Programming Pearls: Bumper-Sticker Computer Science," Communications of the ACM, September 1985) https://en.wikipedia.org/wiki/Ninety%E2%80%93ninety_rule